What we move
- Production machines and assembly lines
- Lifting machines by crane and forklift
- CNC machines, lathes and mills
- Compressors, generators and electrical cabinets
- Racking and warehouse systems
- Packaging equipment and conveyors
- Factory offices and server room
Our process
- 01Factory survey
We map every machine, weight, lifting point and connection, and check the new building's floor, openings and truck access.
- 02Phased plan
A sequence that keeps production running as long as possible, aligned with the plant's schedule.
- 03Dismantling and loading
Labelled, documented disassembly, lifting by forklift or crane, and secure tie-down.
- 04Placement and reassembly
Placement per the new floor plan, mechanical reassembly and connection by technicians, then the next item.
How to minimise production downtime
The key is not to move everything in one day. Start with the warehouse, offices and less critical lines, and leave the main machines for a weekend or holiday. The plant keeps supplying customers almost to the last moment.
Moving a logistics warehouse
In a warehouse the challenge is volume. We work by locations: every pallet is labelled for its destination rack, so the new warehouse is organised from day one.
What a factory relocation includes
| Factory survey and phased plan | Included |
|---|---|
| Numbered machine list with weights and lifting points | Included |
| Mechanical dismantling, labelling and packing | Included |
| Forklifts, heavy-duty skates and transport dollies | Included |
| Trucks and secure tie-down | Included |
| Dedicated project manager | Included |
| Crane and crane truck | As needed |
| Weekend or holiday work | As needed |
| Disconnecting and connecting power, air and controls | The plant's electricians and technicians |
| Levelling and calibrating machines | Manufacturer / plant technician |
| Hazardous materials and waste | Licensed contractor |
What changes with the type of plant
- Machining and metalwork: heavy CNC machines, lathes and presses. Axes are locked per the manufacturer's instructions and the floor load in the new building is checked in advance.
- Electronics and assembly: equipment that is sensitive to static and shocks. It is packed in anti-static packaging and moved in shock-absorbing trucks.
- Production with a cleanroom: equipment going into a cleanroom is cleaned and double-wrapped, and after the move QA tests the room to its class. See Moving equipment into and out of a cleanroom.
Moving within an industrial zone or to another city
Within the same industrial zone the trucks make several runs a day, so a machine can be moved and placed on the same day. For a move to another city we plan full loads, an unloading order that follows the new floor plan and a crew waiting at the other end. We are based in Rehovot and relocate factories in the centre, the south and the north.
How to start
If you are just starting to plan, read our factory relocation timeline and what to check in the new building before signing. For a quote, send a list of machines with weights and photos, and we will get back to you with an initial plan.
Common questions about factory relocation
How long does a factory relocation take?
A small plant can move in a few days. A large plant moves in phases over several weeks. The schedule is set during the initial survey.
Do you provide cranes and forklifts?
Yes. All the lifting equipment needed is coordinated as part of the project.
Who connects the machines at the other end?
We handle placement and mechanical reassembly. Electrical, air and control connections are made by your own electricians and technicians.
How much does a factory relocation cost?
Price depends on the number and weight of machines, lifting equipment and distance. After a site survey we provide a detailed, phased quote.